PROJECT NAME/TITLE: Port Clearing, Transportation, Offloading and Coupling of 2No.30/40MVA Compton Greaves 132/33KV Power Transformer and the accessories.

CLIENT: Stedy Engineering Construction Ltd

LOCATION: Tin Can Port, Lagos to Okiti-Pupa TS Ondo State.

DATE:            2019

PROJECT STATUS: Completed

PROJECT NAME/TITLE:  Shifting of ST04 Generator Transformer (105/140 MVA) on ST01 Plinth and ST01 Generator Transformer (105/140 MVA) on ST04 Plinth

CLIENT: Sapele Power Plant

LOCATION:  Sapele Transmission Station

DATE: 2018

PROJECT STATUS:  Completed

PROJECT NAME/TITLE: Transportation of 150MVA 330/132/33KV Power Transformer Main Tank and its accessories.

CLIENT: Zeman Engineering and Technical Service Ltd

LOCATION: From Shiroro TS, Niger State to Maiduguri TS, Borno State.

DATE:    2015

PROJECT STATUS: Completed

PROJECT NAME/TITLE:  Loading, Movement and Offloading of 100MVA/132/33KV Power Transformer Main Tank to its Plinth.

CLIENT:   T&D Technology Ltd

LOCATION: Egbin Transmission Station, Lagos.

DATE:           2014

PROJECT STATUS:  Completed

PROJECT NAME/TITLE: Emergency Movement of 75MVAR 330KV (Hyusung made) Shunt Reactor Main Tank and its accessories and Construction of Plinth, Skidway and Extension of access road. 

LOCATION:  From Osogbo Transmission Station to Gwagwalada Transmission Station FCT, Abuja.

CLIENT: Transmission Company of Nigeria

DATE:          2014

PROJECT STATUS: Completed

PROJECT NAME/TITLE:  Award OF Contract For: Emergency Removal and Relocation of Burnt 150MVA 330/132/33kV (TBEA MADE) Power Transformer Main tank to a distance of about 180 meters within Osogbo Transmission Station. 

LOCATION: Osogbo Transformer station, Osun State

DATE:            2014

PROJECT STATUS:  Completed

PROJECT NAME/TITLE:  Emergence Relocation of New 150MVA 330/132/33KV (Crompton Greaves Made) Power Transformer Main Tank to a distance of about 160 meters from its new plinth to 4TI Plinth 

CLIENT: Transmission Company of Nigeria

LOCATION: Osogbo Transformer Station.

DATE:          2014.

PROJECT STATUS: Completed

PROJECT NAME/TITLE:Transportation And Delivery Of 1 Number 60mva 132/34.5kv And 1 Number 40mva 132/34.5kv Transformers

CLIENT: Continental Engineering Ltd

LOCATION: From Tin Can Island Port To Ugheli Power Station And Otta Transmission Station

DATE:            2013

PROJECT STATUS:  Completed

PROJECT NAME/TITLE:Electro Mechanical Erection of 100MVA 132/33KV 

CLIENT:  Power Control and Appliances Ltd

LOCATION: Ogba Transmission Station, Lagos State.

DATE: 2014.

PROJECT STATUS: Completed

PROJECT NAME/TITLE: Shifting & Erection of 2x 60 MVA Transformers on Plinth 

LOCATION: Daura Sub-Station, Katsina State.

DATE:       2014

PROJECT STATUS:  Completed

PROJECT NAME/TITLE: Offloading of a Defective 60MVA 132/33KV Power Transformer Main Tank

 

CLIENT: GTA Engineering Ltd

LOCATION: Ikorodu Lagos.

DATE: 2015.

PROJECT STATUS: Completed

 

PROJECT NAME/TITLE:Vacuuming and drying of a 300MVA 330/132/33KV Power Transformer.

LOCATION: Egbin Transmission Station Lagos.

DATE:       2019

PROJECT STATUS:  Completed

PROJECT NAME/TITLE: Dismantling of a 300MVA 330/132/33KV Power Transformer accessories such as Radiators, Bushings, Conservator Tank and Pipes.

 

LOCATION: Egbin Transmission Station, Lagos.

DATE: 2019.

PROJECT STATUS: Completed